Bioconductor 2.5 Release Schedule
September 25
R:
- Start of the release cycle.
BioC:
- Deadline for new package submissions for release with BioC 2.5.
- All BioC package developers should start using R-devel pre-release for testing their packages.
October 7
BioC:
- Release candidate of annotation packages built and posted to devel annotation data repository
October 16
BioC::
- BioC Feature Freeze (beta): no API changes to BioC.
- Deadline for BioC packages passing R CMD build and check without error.
October 23
R::
- R Prerelease.
BioC::
- BioC release candidate 1. Package maintainers should limit changes to "show-stopper" bugs and documentation improvements.
- Deadline for packages passing R CMD build and check without warning. Some warnings will be accepted, clarification on the bioc-devel mailing list.
- Annotation data packages finalized.
October 27
BioC::
- Creation of the BioC 2.5 release branch. Development can resume on trunk, but changes will not be part of the release.
- Build final release repositories.
- Test install scripts, GUI installation.
Octorber 28
BioC::
- BioC 2.5 release.
External Resources
For more information on the release details for R 2.10.0, visit the R Developer Page.